Englewood Cliffs Projects Status

(This page will be updated a day before any scheduled Council meeting)

Project Description:
The scope of the project consists of the resurfacing of Laurie Drive from Johnson Avenue to Roberts Road approximately 2,200 linear feet. The improvements include milling and paving of the roadway, various traffic improvements, spot repair of curbing, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.

Contractor Award Amount Target Completion Last Updated
Your Way Construction, Inc. $258,290.43 11/30/2026 11/10/2026

Paving completed, striping scheduled this week.
 

Project Description:
The scope of the project consists of second phase of Borough-wide Sanitary Sewer Improvements to address the Inflow and Infiltration (I&I) issues. It consists of 12 distinct repair areas. 

Contractor Award Amount Target Completion Last Updated
National Water Main Cleaning Company $1,091,150.00 11/30/2026 11/10/2026

Ground breaking was held on 08/03/2026. Sewer video is completed. Work in progress.

SANITARY SEWER PHASE 1 MAP
SANITARY SEWER PHASE 1 IMPROVEMENTS SUMMARY

Project Description:
The scope of the project consists of reconstruction of last portion of Floyd Street with a total linear length of approximately 1,150 Ft. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, spot repair of curbing, resetting of castings, installation of traffic stripes and marking and other incidental roadway items. Fastech is responsible for Construction Management and Inspection.

Contractor Award Amount Completion Last Updated
D&L Paving Contractors, Inc. $170,176.35 09/24/2026 11/10/2026

Work completed, passed NJDOT inspection. Closeout in process.

Project Description:
The scope of the project consists of construction of a new roadway on unimproved 5th street from border of the borough to the dead end behind 10 Bayview Avenue. Initial investigation is in progress.