Englewood Cliffs Projects Status
Englewood Cliffs Projects Status
(This page will be updated a day before any scheduled Council meeting)
Project Description:
The scope of the project consists of the resurfacing of Laurie Drive from Johnson Avenue to Roberts Road approximately 2,200 linear feet. The improvements include milling and paving of the roadway, various traffic improvements, spot repair of curbing, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| TBD | $- | TBD | 05/12/2026 |
The project is in design phase.
Project Description:
The scope of the project consists of resurfacing of seven Roads in the 2026 Road Resurfacing Program final list with a total linear length of approximately 6,000 Ft. The improvements include milling and paving of the roadway, spot repair of curbing, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| Riverside Co-Op | $398,249.07 | 09/30/2026 | 05/12/2026 |
|
Road Name |
Road Limit |
Status | |
| 1 | 2nd Street | Irving Ave to Bor Limit | Waiting for Pre-Con |
| 2 | Ash Street | Jenkins Dr to Dead End | Waiting for Pre-Con |
| 3 | Center Street | Jenkins Dr to VA Ave | Waiting for Pre-Con |
| 4 | Kahn Ter | Hudson Ter to Sylvan Ave | Waiting for Pre-Con |
| 5 | Clendinen Pl | Hudson Ter to Sylvan Ave | Waiting for Pre-Con |
| 6 | New Street | Hudson Ter to Sylvan Ave | Waiting for Pre-Con |
| 7 | Sherwood Ave | Hudson Ter to Sylvan Ave | Waiting for Pre-Con |
Project Description:
The scope of the project consists of reconstruction of last portion of Floyd Street with a total linear length of approximately 1,150 Ft. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, spot repair of curbing, resetting of castings, installation of traffic stripes and marking and other incidental roadway items. Fastech is responsible for Construction
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| D&L Paving Contractors, Inc. | $170,176.35 | 06/30/2026 | 05/12/2026 |
Pre-construction meeting was held on 04/28/2026. Construction will start in first week of June 2026.
Project Description:
The scope of the project consists of first phase of Borough-wide Sanitary Sewer Improvements to address the Inflow and Infiltration (I&I) issues. The targeted area is on Hudson Terrace between Kahn Terrace and Sherwood Avenue. There will be two 10 ft areas of point lining and one manhole to manhole lining 237 ft long.
Following is the status of the two 10 ft point linings;
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| Montana Construction | $15,200 | 04/29/2026 (DONE) | 05/12/2026 |
237 ft manhole to manhole lining will be done once awarded in the May 13th council meeting.
Project Description:
The scope of the project consists of second phase of Borough-wide Sanitary Sewer Improvements to address the Inflow and Infiltration (I&I) issues. It consists of 12 distinct repair areas. The bid is issued and bid opening date is June 3, 2026.
Project Description:
The scope of the project consists of construction of a new roadway on unimproved 5th street from border of the borough to the dead end behind 10 Bayview Avenue. Preliminary design and initial utility investigation is in progress.