Teaneck Projects Status
Teaneck Projects Status
(This page will be updated a day before any scheduled Council meeting)
Project Description:
The scope of the project consists of:
Reconstruction and expansion of Basketball Court: Removal of existing court, installation of new base, new asphalt pavement, new chain link fence, new surface paint and striping and new lighting fixtures.
Reconstruction of Baseball Field: Removal of existing field, Excavation, grading and drainage, installation of new base and surface, installation of new dugout and sprinkler system.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
Z Tech Contracting, LLC | $817,264.43 | 05/30/2025 | 05/02/2025 |
Awaiting final topsoil and seeding.
Project Description:
The scope of the project consists of:
New Splash Pad: Construction of about 1,000 Sq. Ft Water Splash Pad. The splash pad will be surrounded by a 10 ft wide concrete deck with various site amenities like benches and trash receptacles, all plumbing and an access walkway to get to the Splash Pad.
New Restroom: Installation of a new prefab restroom structure, Construction of concrete pad, and all relevant plumbing, electrical and drainage.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
Ray Palmer Associates, Inc. | $588,000 | 05/30/2025 | 05/02/2025 |
Splash Pad:
Splash pad and fencing are nearing completion.
Restroom:
Requires final inspections.
Project Description:
The scope of the project consists of removal of existing Playground equipment, install new playground equipment, new playground surface and installation of other site amenities.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
ADP Group, Inc. | $457,630 | 05/30/2025 | 05/02/2025 |
Safety surface installation was done last week.
Project Description:
The scope of the project consists of the conversion of Tennis court in four Pickleball courts in Andreas Park. The improvements include resurfacing of current surface, installation of chain-link fence 4 feet high between the courts and new surface paint and striping for Pickleball layouts based on design documents as provided.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
Green Valley Group Inc. | $156,100 | 05/30/2025 | 05/02/2025 |
Contractor finished paving and concrete work and is waiting to do the surface painting and striping, Project will be finished in May.
Project Description:
The scope of the project consists of construction of Votee Park restroom at the northern section of Votee Park. The new Restroom will be brand new prefab 9 Feet 4 inches by 20 Feet structure exactly like the one installed in Phelps Park, with 3 restrooms, one for each gender, one for family and a storage area, utilities and other incidental items.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
AB Contracting, LLC | $314,800 | 05/30/2025 | 05/02/2025 |
Construction is completed. Pending punch list.
Project Description:
The scope of the project consists of resurfacing of all Roads in the 2023 Road Resurfacing Program final list with a total linear length of over 2 miles. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items. The scope includes full depth reconstruction of Hemlock Drive North including new drainage and tie-in to the town drainage system.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
4 Clean Up, Inc. | $1,170,635.75 | 05/30/2025 | 05/02/2025 |
Punch list items to be completed in the spring 2025.
Project Description:
The scope of the project consists of the resurfacing of Palisades Avenue from Englewood Avenue to Amsterdam Avenue. The improvements include milling and paving of the roadway, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking, spot repair of concrete curb and sidewalk, replacement of curb piece with type N – ECO and other incidental roadway items.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
New Prince Concrete Construction Co., Inc. | $259,479 | 05/30/2025 | 05/02/2025 |
Punch list items to be completed in Spring 2025.
Project Description:
The scope of the project consists of the resurfacing of Argonne Court approximately 300 Linear feet, Hirliman Road approximately 560 feet, Schoonmaker Road approximately 590 Linear feet and Nelden Road from Schoonmaker Road to Westervelt Place approximately 240 Linear feet. The improvements include milling and paving of the roadways, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking, spot repair of concrete curb and sidewalk, replacement of curb piece with type N – ECO and other incidental roadway items.
Contractor | Award Amount | Completion | Last Updated |
---|---|---|---|
DLS Contracting, Inc. | $168,646 | 12/31/2024 | 05/02/2025 |
The project is complete and closing documents have been submitted to CDBG.
Project Description:
The scope of work involves the design, permitting, and construction management of a 90,000-gallon stormwater detention system. The system is intended to manage stormwater runoff for Belle Avenue area, ensuring compliance with local, state, and federal regulations related to stormwater management, sustainability, and flood prevention.
Last Updated: 05/02/2025
Plans were sent to EPA and NJDEP.
Last Updated: 05/02/2025
Survey is approved. Compensation fee need to be resolved. The township has passed a resolution to lease the subject land from NJDEP while the diversion permit is being worked on. We have sent the request to NJDEP to execute a lease and waiting for their response.
Last Updated: 05/02/2025
Application was submitted. EPA grant agreement is received.
Project Description:
The scope of work includes the design, Geotech testing management, and construction management for the installation of 9 bioswale to improve stormwater management, enhance water quality, and promote ecological benefits. The bioswale will be designed to capture runoff, filter pollutants, and allow water infiltration into the soil.
Last Updated: 05/02/2025
Geotechnical testing took place last week.
Project Description:
The scope of the project consists of structural inspection of the pedestrian bridge over Palisade Avenue, Windsor Road and CSX Railroad. The project also include design and construction of prioirty repairs. The pedestrian bridge structure consists of a five span, simply supported through-girder bridge supporting a 7’-3” wide, 6” thick concrete deck, transverse floorbeams span between the main steel girders. The bridge servers as a connection bewteen Windsor Road and Palisades Avenue, crossing over three railroad tracks used by CSX transportation railroad.
Last Updated: 05/02/2025
Township is coordinating with CSX for design document review.
Project Description:
The scope of the project consists of the resurfacing of Fycke Lane from Teaneck Road to Glenwood Avenue border approximately 2,900 linear feet. The improvements include milling and paving of the roadway, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.
Last Updated: 05/02/2025
Contract awarded to D&L and pre-con meeting was held last week, construction should start next month.
Project Description:
The scope of the project consists of the reconstruction of all four Tennis courts in Argonne Park. The improvements include repair of concrete border, excavation and removal of the current Tennis court, installation of new base, new asphalt pavement surface, installation of new chain link fence, and new surface paint and striping for both Tennis and Pickleball layouts.
Last Updated: 05/02/2025
Contract awarded to Dakota Excavating Contractor and pre-con meeting will be held next week.
Project Description:
The scope of the project consists of construction of a 1,000 Sq. Ft Water Splash Pad at Phelps Park right next to the new restroom. The splash pad will be surrounded by a 5 ft wide concrete deck with various site amenities like benches and trash receptacles and an access walkway to get to the Splash Pad.
Last Updated: 05/02/2025
Design is completed. Awaiting funding availability.
Project Description:
The scope of the project consists of 3 main amenities as described below.
Replacement of Children Playground: Removal of existing Playground equipment, install new playground equipment, new playground surface and installation of other site amenities for two separate play areas. One for 2-5 years old and another for 5-12 years old children.
New Splash Pad: Construction of about 1,000 Sq. Ft Water Splash Pad. The splash pad will be surrounded by a 10 ft wide concrete deck with various site amenities like benches and trash receptacles, all plumbing and an access walkway to get to the Splash Pad.
New Restroom: Installation of a new prefab restroom structure, Construction of concrete pad, and all relevant plumbing, electrical and drainage.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Last Updated: 05/02/2025
Preliminary design is in progress.
Project Description:
The scope of the project consists of resurfacing of all Roads in the 2024 Road Resurfacing Program final list with a total linear length of over 3 miles. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items. The scope includes full depth reconstruction of Hemlock Drive North including new drainage and tie-in to the town drainage system.
Last Updated: 05/02/2025
Bid opening was on April 15, 2025.
Project Description:
Maple Avenue is a concrete street. The scope of the project consists of the concrete repair of Maple Avenue from Lincoln Place to Helen Street approximately 800 Linear feet. The improvements include selective concrete repair of the roadways, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking, spot repair of concrete curb and sidewalk, replacement of curb piece with type N – ECO and other incidental roadway items.
Last Updated: 05/02/2025
Design is completed. Awaiting funding and County review of plans.