Teaneck Projects Status
Teaneck Projects Status
(This page will be updated a day before any scheduled Council meeting)
Project Description:
The scope of the project consists of resurfacing of all Roads in the 2024 Road Resurfacing Program final list with a total linear length of over 3 miles. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items. The scope includes full depth reconstruction of Hemlock Drive North including new drainage and tie-in to the town drainage system.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| D&L Paving Contractors, Inc. | $1,683,741.38 | 12/31/2025 | 02/23/2026 |
Milling and paving finished for this season. Waiting for spring to work on the punchlist
Here is the list of Roadways to be paved under 2024 Roadway Resurfacing Program:
|
Road Name |
Road Limit |
Status | |
| 1 | Suffern Rd | River Rd. to Wilson Ave. | Completed |
| 2 | Magnolia Rd | Billington Rd. to E. Laurelton Pkwy. | Completed |
| 3 | Princeton Rd | E. Laurelton Pkwy Intersection | Completed |
| 4 | Somerset Rd | Sunderland Rd. to Wendel Pl. | Completed |
| 5 | Hanover St | Winthrop Rd. to Dead End | Completed, pending punch list items |
| 6 | Ogden Ave | Rugby Rd. to Sussex Rd. | Completed, pending punch list items |
| 7 | Churchill Rd | Rugby Rd. to Sussex Rd. | To be scheduled |
| 8 | Van Buskirk Rd | Teaneck Rd. to Van Cortlandt Ter. | Completed |
| 9 | E. Englewood Ave | House #56 to House #66 | Completed |
| 10 | W. Englewood Ave | Queen Anne Rd. to Hill St. | Completed |
| 11 | Selvage Ave | Margaret St. to Stasia Rd. | Completed |
| 12 | Farragut Ct | Farragut Dr. to Dead End | To be scheduled |
| 13 | Werner Pl | Teaneck Rd. to Prince St. | To be scheduled |
| 14 | Ridgeway St | Cherry Ln. to Edgemont Pl. | To be scheduled |
| 15 | Broad St | Cedar Ln. to Merrison St. | To be scheduled |
| 16 | Sandburg Ct Drainage | Glenpointe @ Lucy Ave. Easement | Completed |
| 17 | Washington St | Glenwood Ave. to Dead End | To be scheduled |
| 18 | Fabry Terr | Glenwood Ave. to Kilmurray Dr. | To be scheduled |
| 19 | Herrick Ave | Mildred St. to Albin St. | To be scheduled |
| 20 | Pine St | Queen Anne Rd. to Palmer Ave. | Completed, pending punch list items |
| 21 | Cane St | Palmer Ave. to Bogota Border | Completed |
| 22 | Walnut St | Teaneck Rd. to Lees Ave. | Completed |
| 23 | Maple St | Teaneck Rd. to Lees Ave. | Completed |
| 24 | John St | 541 John St. to Grant Ter. | Completed |
| A | Ward Plaza, Eastbound lane | Teaneck Rd. to 30 Ward Plaza | Completed |
| B | Golf Ct | Teaneck Rd. to Club Rd. | To be scheduled |
| C | Golf Ct | Club Rd. to Country Club Dr. | To be scheduled |
| D | Fayette St | Sunderland Rd. to Grenville Ave. | Completed |
Project Description:
Maple Avenue is a concrete street. The scope of the project consists of the concrete repair of Maple Avenue from Lincoln Place to Helen Street approximately 800 Linear feet. The improvements include selective concrete repair of the roadways, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking, spot repair of concrete curb and sidewalk, replacement of curb piece with type N – ECO and other incidental roadway items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| D&L Paving Contractors, Inc. | $ 247,962.60 | 03/15/2026 | 02/23/2026 |
CDBG closeout completed. Waiting for spring to work on the punchlist.
Project Description:The scope of the project consists of the resurfacing of Palisades Avenue from Tryon Avenue West to Dead End, Tryon Avenue West from Palisades Avenue to Queen Anne Road and Galway Place from Palisades Avenue to Dead End. The improvements include milling and paving of the roadway, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking, spot repair of concrete curb and sidewalk, replacement of curb piece with type N – ECO, Drainage improvements and other incidental roadway items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| Cifelli & Sons | $ 281,579.25 | 03/31/2026 | 02/23/2026 |
Construction started in November. Concrete work is completed, milling and paving will be done in spring. Manhole covers were placed as part of additional work.
Project Description:
The scope of the project consists of construction of a 1,000 Sq. Ft Water Splash Pad at Phelps Park right next to the new restroom. The splash pad will be surrounded by a 5 ft wide concrete deck with various site amenities like benches and trash receptacles and an access walkway to get to the Splash Pad.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| Green Valley Group Inc. | $346,750.00 | 05/15/2026 | 02/23/2026 |
Contractor finished working on the water line and passed inspections. Equipment arrived, meter connection and equipment installation is on hold due to weather.
Project Description:The scope of the project consists of complete design and bid specifications of Exercise Stations in Brooks Park.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
|
Thomas & Sons Builders LLC dba Develop Builders |
$180,680.00 | 02/28/2026 | 02/23/2026 |
Poured concrete on 01/22/26. Forms were removed and sawcutting was completed. Equipment was installed and safety surfacing is on hold due to weather.
Project Description:
The scope of work includes the design, Geotech testing management, and construction management for the installation of 9 bioswale to improve stormwater management, enhance water quality, and promote ecological benefits. The bioswale will be designed to capture runoff, filter pollutants, and allow water infiltration into the soil.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
|
A-Tech Concrete Co. Inc. |
$258,670.00 | 05/15/2026 | 02/23/2026 |
Shop drawings were approved. Waiting for construction to start in March 2026.
Project Description: The scope of the project consists of the replacement of approximately 800 LF of 8” clay Sewer mian, beginning at sanitary sewer manhole at the intersection of Teaneck Road and Livingson Place and proceding west to Manholes at the intersection of Livingston Place and Palisade Avenue and to the dead end of Clinton Place. The existing 8” clay sewer main ranges from 6’ to 7’ in depth and is over 90 years old. The construction cost will be covered by a supplemental Community Development Block Grant (CDBG) of $250,000 that needs to be utilized by end of 1Q2026. All connections to the residences will be reconnected into the new sewer main as part of this project.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
|
Matina & Son Inc. |
$367,500.00 | 04/30/2026 | 02/23/2026 |
Pre-construction meeting was held on 01/13/2026. Construction will start in March 2026.
Project Description: The scope of the project consists of development of engineering plans and related construction management and inspection services for Construction of Brooks Park restroom. The new Restrooms will be brand new prefab 9 Feet 4 inches by 20 Feet structure exactly like the one installed in Phelps Park, with 3 restrooms, one for each gender, one for family and a storage area, utilities and other incidental items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
|
Thomas & Sons Builders LLC dba Develop Builders |
$307,373.00 | 02/28/2026 | 02/23/2026 |
Bids were opened on 02/10/2026. Apparent Lowest bidder is Develop Builders with the total bid of $307,373.00. Waiting for the Award of contract.
Project Description:
The scope of the project consists of structural inspection of the pedestrian bridge over Palisade Avenue, Windsor Road and CSX Railroad. The project also include design and construction of prioirty repairs. The pedestrian bridge structure consists of a five span, simply supported through-girder bridge supporting a 7’-3” wide, 6” thick concrete deck, transverse floorbeams span between the main steel girders. The bridge servers as a connection bewteen Windsor Road and Palisades Avenue, crossing over three railroad tracks used by CSX transportation railroad.
Last Updated: 02/23/2026
Plans are completed for the priority repair.
Project Description: The scope of the project consists of development of engineering specifications and related construction management and inspection services for installation of High Volume Low Speed Fans in Richard Rodda Community Center.
Last Updated: 02/23/2026
Specifications are in progress.
Project Description:The scope of the project consists of construction of Griggs Avenue, Van Buren Avenue and Herrick Avenue from Palisade Avenue to dead end by Herrick Park. The improvements include full construction of the roadways including curbs, base construction and paving, installation of traffic stripes and marking and other incidental roadway items.
Last Updated: 02/23/2026
Project is out to bid. Bid opening is scheduled for 03/03/2026.
Project Description:
The scope of the project consists of 2 main amenities as described below.
Replacement of Children Playground: Removal of existing Playground equipment, install new playground equipment, new playground surface and installation of other site amenities for two separate play areas. One for 2-5 years old and another for 5-12 years old children.
New Restroom: Installation of a new prefab restroom structure, Construction of concrete pad, and all relevant plumbing, electrical and drainage.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Last Updated: 02/23/2026
Design is in final review.
Project Description:The scope of the project consists of the roadway improvements to Bilton Street, Livingston Place, and Clinton Place. The improvements include milling and paving, spot repairs of curbs and driveway aprons, installation of bicycle-safe grates and N-ECO curb pieces, addition of ADA-compliant curb ramps, and new pavement markings.
Last Updated: 02/23/2026
Design approved by CBDG, waiting for bid ad to publish.
Project Description:
The scope of work involves the design, permitting, and construction management of a 187,000-gallon stormwater detention system. The system is intended to manage stormwater runoff for Belle Avenue area, ensuring compliance with local, state, and federal regulations related to stormwater management, sustainability, and flood prevention.
| Contractor | Award Amount | Completion | Last Updated |
|---|---|---|---|
|
Matina & Son, Inc. |
$ 1,004,435.00 | 11/06/2025 | 02/23/2026 |
EPA project closeout in process.
Last Updated: 02/23/2026
Working on the paperwork for final application.
Last Updated: 02/23/2026
Application was submitted. EPA grant agreement is received.
Project Description:
The scope of the project consists of the resurfacing of Fycke Lane from Teaneck Road to Glenwood Avenue border approximately 2,900 linear feet. The improvements include milling and paving of the roadway, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.
| Contractor | Award Amount | Completion | Last Updated |
|---|---|---|---|
| D&L Paving Contractors, Inc. | $415,424.59 | 09/15/2025 | 02/23/2026 |
DOT project closeout completed. Processing retainage payment.
Project Description:
The scope of the project consists of the reconstruction of all four Tennis courts in Argonne Park. The improvements include repair of concrete border, excavation and removal of the current Tennis court, installation of new base, new asphalt pavement surface, installation of new chain link fence, and new surface paint and striping for both Tennis and Pickleball layouts.
| Contractor | Award Amount | Completion | Last Updated |
|---|---|---|---|
| Dakota Excavating Contractor, Inc. | $449,320 |
09/15/2025 |
02/23/2026 |
Waiting for the PO for paint repair.
Project Description:
The scope of the project consists of:
New Splash Pad: Construction of about 1,000 Sq. Ft Water Splash Pad. The splash pad will be surrounded by a 10 ft wide concrete deck with various site amenities like benches and trash receptacles, all plumbing and an access walkway to get to the Splash Pad.
New Restroom: Installation of a new prefab restroom structure, Construction of concrete pad, and all relevant plumbing, electrical and drainage.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
| Contractor | Award Amount | Completion | Last Updated |
|---|---|---|---|
| Ray Palmer Associates, Inc. | $588,000 | 09/15/2025 | 02/23/2026 |
Project is completed. Waiting for pressure test of splash pad in spring.