Teaneck Projects Status
Teaneck Projects Status
(This page will be updated a day before any scheduled Council meeting)
Project Description:
The scope of the project consists of resurfacing of all Roads in the 2025 Road Resurfacing Program final list with a total linear length of around 2 miles. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| DLS Contracting Inc. | $ 1,198,091.20 | 10/01/2026 | 10/05/2026 |
Paving completed. Punchlist remaining.
Here is the list of Roadways paved under 2025 Roadway Resurfacing Program:
|
Road Name |
Road Limit |
Status |
|
| 1 | Terhune St | Larch Ave to Elm St | Completed |
| 2 | Windsor Road | Cedar Ln to Beverly Rd | Completed |
| 3 | Beverly Road | Garrison Ave to Williams Ave | Completed |
| 4 | Claremont Avenue | Garrison Ave to Belle Ave | Completed |
| 5 | Billington Road | Windsor rd to Magnolia Rd | Completed |
| 6 | E Laurelton Pkwy | Belle Ave to Magnolia Rd | Completed |
| 7 | Essex Road | Rutland Ave to W Englewood Ave | Completed |
| 8 | Rutland Ave | Essex Rd to Hudson Rd | Completed |
| 9 | Berkeley Street | Manhattan Ave to Dead End | Completed |
| 10 | Church Street | Teaneck rd to Alicia Ave | Completed |
| 11 | Summit Avenue | Robinson St to Prospect terr | Completed |
| 12 | Alpine Drive | E lawn Dr to Midwood Rd | Completed |
| 13 | Salem street | Lindbergh Blvd to End of street | Completed |
| 14 | Howard Street | Lindbergh Blvd to Dead End | Completed |
| 15 | George Street | Lindbergh Blvd to Dead End | Completed |
| 16 | John Street | Fycke Ln to Washington St | Completed |
| 17 | Johnson Court | Johnson Ave to Dead End | Completed |
| A | Club Rd | Cedar Ln to Bennett Rd | Completed |
| B | Bedford Avenue | Arlington Ave to Teaneck Rd | Completed |
| C | Woods Rd | Windsor Rd to Grace Terr | Completed |
Project Description: The scope of the project consists of development of engineering plans and related construction management and inspection services for Construction of Brooks Park restroom. The new Restrooms will be brand new prefab 9 Feet 4 inches by 20 Feet structure exactly like the one installed in Phelps Park, with 3 restrooms, one for each gender, one for family and a storage area, utilities and other incidental items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
|
Thomas & Sons Builders LLC dba Develop Builders |
$307,373.00 | 10/15/2026 | 10/05/2026 |
Utility work for the sewer and water connections has been completed. The restroom foundation has been completed, and the building was delivered on September 24th.
Project Description:The scope of the project consists of construction of Griggs Avenue, Van Buren Avenue and Herrick Avenue from Palisade Avenue to dead end by Herrick Park. The improvements include full construction of the roadways including curbs, base construction and paving, installation of traffic stripes and marking and other incidental roadway items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
|
DLS Contracting, Inc. |
$264,236.00 | 09/15/2026 | 10/05/2026 |
Closeout is in process.
Project Description:The scope of the project consists of the roadway improvements to Bilton Street, Livingston Place, and Clinton Place. The improvements include milling and paving, spot repairs of curbs and driveway aprons, installation of bicycle-safe grates and N-ECO curb pieces, addition of ADA-compliant curb ramps, and new pavement markings.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
|
DLS Contracting, Inc. |
$170,000.00 | 09/15/2026 | 10/05/2026 |
Punchlist pending.
Project Description:
The scope of the project consists of 2 main amenities as described below.
Replacement of Children Playground: Removal of existing Playground equipment, install new playground equipment, new playground surface and installation of other site amenities for two separate play areas. One for 2-5 years old and another for 5-12 years old children.
New Restroom: Installation of a new prefab restroom structure, Construction of concrete pad, and all relevant plumbing, electrical and drainage.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
|
Green Valley Group, Inc. |
$921,750.00 | Spring 2027 | 10/05/2026 |
Sidewalk concrete and inlet installation completed. The demolition process has been completed. Playground grading and the detention systems have been completed. Foundation work for the restroom is expected to be completed this week.
Project Description:
The scope of this project consists of the installation of approximately 1,100 linear feet of 18-inch reinforced concrete pipe (RCP) storm sewer main, beginning at an existing storm inlet located approximately 80 feet north of the intersection of River Road and Kip Street. The new storm sewer will proceed east along Kip Street, passing through the intersection of Kip Street and Catalpa Avenue, and terminate at an existing inlet at the intersection of Larch Avenue.
As part of the project, four new storm inlets will be constructed, and two existing storm inlets will be reconstructed. The existing inlets are leaching inlets that have begun to collapse due to unstable subsurface conditions surrounding the structures.
The construction cost will be partially offset by approximately $115,000 in remaining funds from the EPA grant awarded for the Sagamore Detention Project. The EPA has approved the use of these remaining grant funds for this project.
Last Updated: 10/05/2026
Bids were opened on 09/29/2026. Lowest bidder is Persistent Construction, Inc. with total bid of $254,955.00. Waiting for the award of contract.
Project Description: The scope of the project consists of development of engineering specifications and related construction management and inspection services for installation of High Volume Low Speed Fans in Richard Rodda Community Center.
Last Updated: 10/05/2026
Contract has been awarded to TM Brennan Service Inc. for a total bid of $74,250.00.
Project Description:
The scope of the project consists of structural inspection of the pedestrian bridge over Palisade Avenue, Windsor Road and CSX Railroad. The project also include design and construction of prioirty repairs. The pedestrian bridge structure consists of a five span, simply supported through-girder bridge supporting a 7’-3” wide, 6” thick concrete deck, transverse floorbeams span between the main steel girders. The bridge servers as a connection bewteen Windsor Road and Palisades Avenue, crossing over three railroad tracks used by CSX transportation railroad.
Last Updated: 10/05/2026
Waiting for signed documents from GFT.
Project Description:
The scope of work involves the design and construction management of a 90 ft. synthetic turf multipurpose field. The field could be used for baseball, softball, football, full size soccer or two U9 soccer fields through multi-striping.
Last Updated: 10/05/2026
Survey is being carried out.
Project Description:
The scope of the project consists of development of engineering plans and related construction management and inspection services for construction of a 1,000 Sq. Ft Water Splash Pad at Argonne Park and a new restroom close to the existing tennis courts. The splash pad will be surrounded by a 5 ft wide concrete deck with various site amenities like benches and trash receptacles and an access walkway to get to the Splash Pad. The new Restrooms will be a brand new prefab 9 Feet 4 inches by 20 Feet structure exactly like the one installed in Phelps Park, with 3 restrooms, one for each gender, one for family and a storage area, utilities and other incidental items.
Last Updated: 10/05/2026
Design is in progress.
Project Description:
The scope of the project consists of conducting a truck traffic study for Country Club Drive from East Cedar Lane to East Lawn Drive to evaluate the proposed restriction of commercial motor vehicle (CMV) traffic at all times, while allowing access for local deliveries. The study will include traffic volume and vehicle classification counts, review of crash history, evaluation of existing roadway and traffic conditions, identification of potential truck entrapment locations, and evaluation of alternate routes available for commercial motor vehicles. The project will also include preparation of the required engineering recommendations, certifications, supporting documentation, and coordination with affected roadway authorities, as necessary, for submission to the New Jersey Department of Transportation (NJDOT) for review and approval.
Last Updated: 10/05/2026
Project is in initial planning.