Teaneck Projects Status
Teaneck Projects Status
(This page will be updated a day before any scheduled Council meeting)
Project Description:
The scope of the project consists of construction of Votee Park restroom at the northern section of Votee Park. The new Restroom will be brand new prefab 9 Feet 4 inches by 20 Feet structure exactly like the one installed in Phelps Park, with 3 restrooms, one for each gender, one for family and a storage area, utilities and other incidental items.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
AB Contracting, LLC | $314,800 | 03/31/2025 | 03/11/2025 |
The building has been delivered. Utility connections are expected to be completed within 2–3 weeks.
Concrete and other site work are scheduled for completion in the spring.
Project Description:
The scope of the project consists of:
Reconstruction and expansion of Basketball Court: Removal of existing court, installation of new base, new asphalt pavement, new chain link fence, new surface paint and striping and new lighting fixtures.
Reconstruction of Baseball Field: Removal of existing field, Excavation, grading and drainage, installation of new base and surface, installation of new dugout and sprinkler system.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
Z Tech Contracting, LLC | $817,264.43 | 04/30/2025 | 03/11/2025 |
Baseball Field:
The diamond/infield has been prepared.
Rough grading of the outfield and necessary retaining walls are complete.
Fence and backstop installation is finished.
Basketball Court:
Perimeter curbing is complete, and fence work is underway.
Poles and backboards have been installed. Benches are in place.
Gravel walkways have been laid; paving will proceed as weather permits.
Project Description:
The scope of the project consists of:
New Splash Pad: Construction of about 1,000 Sq. Ft Water Splash Pad. The splash pad will be surrounded by a 10 ft wide concrete deck with various site amenities like benches and trash receptacles, all plumbing and an access walkway to get to the Splash Pad.
New Restroom: Installation of a new prefab restroom structure, Construction of concrete pad, and all relevant plumbing, electrical and drainage.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
Ray Palmer Associates, Inc. | $588,000 | 04/30/2025 | 03/11/2025 |
Splash Pad:
Equipment has been delivered.
The contractor has passed building, plumbing and electrical bonding inspections and poured the concrete pad.
Site work will be completed in the spring.
Restroom:
The building is installed, and electrical and plumbing connections are in progress, with inspections forthcoming.
Site work will be completed in the spring.
Project Description:
The scope of the project consists of removal of existing Playground equipment, install new playground equipment, new playground surface and installation of other site amenities.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
ADP Group, Inc. | $457,630 | 04/30/2025 | 03/11/2025 |
Most play equipment has been installed.
The sidewalk around the playground is 80% complete.
Retaining walls are finished; minor grading is pending.
Rubber safety surfacing will be installed in the spring.
Project Description:
The scope of the project consists of resurfacing of all Roads in the 2023 Road Resurfacing Program final list with a total linear length of over 2 miles. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items. The scope includes full depth reconstruction of Hemlock Drive North including new drainage and tie-in to the town drainage system.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
4 Clean Up, Inc. | $1,170,635.75 | 04/30/2025 | 03/11/2025 |
Remaining punch list items are scheduled for completion in the spring.
Project Description:
The scope of the project consists of the resurfacing of Palisades Avenue from Englewood Avenue to Amsterdam Avenue. The improvements include milling and paving of the roadway, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking, spot repair of concrete curb and sidewalk, replacement of curb piece with type N – ECO and other incidental roadway items.
Contractor | Award Amount | Target Completion | Last Updated |
---|---|---|---|
New Prince Concrete Construction Co., Inc. | $259,479 | 04/30/2025 | 03/11/2025 |
Punch list items will be completed in the spring.
Project Description:
The scope of the project consists of the resurfacing of Argonne Court approximately 300 Linear feet, Hirliman Road approximately 560 feet, Schoonmaker Road approximately 590 Linear feet and Nelden Road from Schoonmaker Road to Westervelt Place approximately 240 Linear feet. The improvements include milling and paving of the roadways, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking, spot repair of concrete curb and sidewalk, replacement of curb piece with type N – ECO and other incidental roadway items.
Contractor | Award Amount | Completion | Last Updated |
---|---|---|---|
DLS Contracting, Inc. | $168,646 | 12/31/2024 | 03/11/2025 |
The project is complete and closing documents have been submitted to CDBG.
Project Description:
The scope of the project consists of construction of Sidewalk, ADA curb ramps and installation of detectable warning surfaces at Cedar Lane (from Hackensack Border to Teaneck Road) and Teaneck Road (from Ridgefield Border to Cedar Lane).
Contractor | Completion | Last Updated |
---|---|---|
DLS Contracting, Inc. | 12/31/2024 | 03/11/2025 |
The project is complete.
Project Description:
The scope of the project consists of installation of new lights for the Tennis courts in Votee Park. The improvements include removal of current lights, installation of foundations for new lights, rewiring for new lights including automation and remote management.
Contractor | Award Amount | Completion | Last Updated |
---|---|---|---|
Quality Electrical Construction | $148,200 | 11/04/2024 | 03/11/2025 |
Project is completed.
Project Description:
The scope of the project consists of installation of 25 ft x 50 ft Arc Cantilever Shade structure with fabric canopy and metal columns, on southern side of splash pad and installation of a custom 34 ft x 52 ft steel gable shelter with concrete pad on northern side of the splash pad, grading, site restoration and other incidental items.
Contractor | Award Amount | Completion | Last Updated |
---|---|---|---|
AB Contracting, LLC | $448,900 | 11/01/2024 | 03/11/2025 |
Project is completed including punch list items.
Project Description:
The scope of work involves the design, permitting, and construction management of a 90,000-gallon stormwater detention system. The system is intended to manage stormwater runoff for Belle Avenue area, ensuring compliance with local, state, and federal regulations related to stormwater management, sustainability, and flood prevention.
Last Updated: 03/11/2025
Design is in progress.
Last Updated: 03/11/2025
Survey is approved. Compensation fee need to be resolved. The township has passed a resolution to lease the subject land from NJDEP while the diversion permit is being worked on. We have sent the request to NJDEP to execute a lease and waiting for their response.
Last Updated: 03/11/2025
Application was submitted. EPA grant agreement is received.
Project Description:
The scope of work includes the design, Geotech testing management, and construction management for the installation of 9 bioswale to improve stormwater management, enhance water quality, and promote ecological benefits. The bioswale will be designed to capture runoff, filter pollutants, and allow water infiltration into the soil.
Last Updated: 03/11/2025
Design has been started.
Project Description:
The scope of the project consists of structural inspection of the pedestrian bridge over Palisade Avenue, Windsor Road and CSX Railroad. The project also include design and construction of prioirty repairs. The pedestrian bridge structure consists of a five span, simply supported through-girder bridge supporting a 7’-3” wide, 6” thick concrete deck, transverse floorbeams span between the main steel girders. The bridge servers as a connection bewteen Windsor Road and Palisades Avenue, crossing over three railroad tracks used by CSX transportation railroad.
Last Updated: 03/11/2025
Draft plans were received.
Coordination with CSX is required during both phases of engineering and construction.
As the manual explains, the Sponsoring Agency (of the project, Teaneck) will need to enter into a Preliminary Engineering Agreement with CSX. Stemming from that review, CSX provides the project sponsor with an estimate of CSX costs for the construction phase.
Township attorney is trying to reach out to CSX for an agreement.
Project Description:
The scope of the project consists of the resurfacing of Fycke Lane from Teaneck Road to Glenwood Avenue border approximately 2,900 linear feet. The improvements include milling and paving of the roadway, various traffic improvements, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.
Last Updated: 03/11/2025
The project is in bidding phase. Bid Opening date is 03/25/2025.
Project Description:
The scope of the project consists of the reconstruction of all four Tennis courts in Argonne Park. The improvements include repair of concrete border, excavation and removal of the current Tennis court, installation of new base, new asphalt pavement surface, installation of new chain link fence, and new surface paint and striping for both Tennis and Pickleball layouts.
Last Updated: 03/11/2025
The Project is in bidding phase. The bid opening date is 03/25/2025.
Project Description:
The scope of the project consists of construction of a 1,000 Sq. Ft Water Splash Pad at Phelps Park right next to the new restroom. The splash pad will be surrounded by a 5 ft wide concrete deck with various site amenities like benches and trash receptacles and an access walkway to get to the Splash Pad.
Last Updated: 03/11/2025
Final design documents are being completed. Met with recreated department to finalize the play equipment.
Project Description:
The scope of the project consists of 3 main amenities as described below.
Replacement of Children Playground: Removal of existing Playground equipment, install new playground equipment, new playground surface and installation of other site amenities for two separate play areas. One for 2-5 years old and another for 5-12 years old children.
New Splash Pad: Construction of about 1,000 Sq. Ft Water Splash Pad. The splash pad will be surrounded by a 10 ft wide concrete deck with various site amenities like benches and trash receptacles, all plumbing and an access walkway to get to the Splash Pad.
New Restroom: Installation of a new prefab restroom structure, Construction of concrete pad, and all relevant plumbing, electrical and drainage.
General site improvements such as access walkways, landscaping, asphalt surfacing, site restoration, grading and drainage and other incidental items are also included in the scope.
Last Updated: 03/11/2025
Preliminary Assessment Report is approved by the DEP. Currently working on the preliminary design.
Project Description:
The scope of the project consists of resurfacing of all Roads in the 2024 Road Resurfacing Program final list with a total linear length of over 3 miles. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, resetting of castings, installation of traffic stripes and marking and other incidental roadway items. The scope includes full depth reconstruction of Hemlock Drive North including new drainage and tie-in to the town drainage system.
Last Updated: 03/11/2025
The list of roadways is finalized and preliminary design completed. Working on detailed design.
Here is the list of the roads for 2024 Roadway Resurfacing
1. |
BROAD STREET |
2. |
CANE STREET |
3. |
CHURCHILL ROAD |
4. |
E. LAURELTON PKWY |
5. |
ENGLEWOOD AVE |
6. |
FABRY TERRACE |
7. |
FARRAGUT COURT |
8. |
HANOVER STREET |
9. |
HERRICK AVE |
10. |
JOHN STREET |
11. |
MAGNOLIA ROAD |
12. |
MAPLE STREET |
13. |
OGDEN AVE |
14. |
PINE STREET |
15. |
RIDGEWAY STREET |
16. |
SELVAGE AVE |
17. |
SOMERSET ROAD |
18. |
SUFFERN ROAD |
19. |
VAN BUSKIRK ROAD |
20. |
WALNUT STREET |
21. |
WASHINGTON STREET |
22. |
WERNER PLACE |
ALTERNATES | |
A. |
WARD PLAZA |
B. |
GOLF COURT SECTION 1 |
C. |
GOLF COURT SECTION 2 |
D. |
FAYETTE STREET |