Project Description:
The scope of the project consists of the resurfacing of Laurie Drive from Johnson Avenue to Roberts Road approximately 2,200 linear feet. The improvements include milling and paving of the roadway, various traffic improvements, spot repair of curbing, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| TBD | $- | TBD | 07/07/2026 |
The project is in design phase and the final plans were just sent to NJDOT
Project Description:
The scope of the project consists of resurfacing of seven Roads in the 2026 Road Resurfacing Program final list with a total linear length of approximately 6,000 Ft. The improvements include milling and paving of the roadway, spot repair of curbing, resetting of castings, installation of traffic stripes and marking and other incidental roadway items.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| Riverside Co-Op(DLS) | $398,249.07 | 09/30/2026 | 07/07/2026 |
|
Road Name |
Road Limit |
Status | |
| 1 | 2nd Street | Irving Ave to Bor Limit | Paved |
| 2 | Ash Street | Jenkins Dr to Dead End | Milling in progress |
| 3 | Center Street | Jenkins Dr to VA Ave | Milling in progress |
| 4 | Kahn Ter | Hudson Ter to Sylvan Ave | Paved |
| 5 | Clendinen Pl | Hudson Ter to Sylvan Ave | Milling in progress |
| 6 | New Street | Hudson Ter to Sylvan Ave | Paved |
| 7 | Sherwood Ave | Hudson Ter to Sylvan Ave | Paved |
Project Description:
The scope of the project consists of reconstruction of last portion of Floyd Street with a total linear length of approximately 1,150 Ft. The improvements include milling and paving of the roadway, reconstruction of the handicap ramps according to the ADA standards and installation of detectable warning surfaces, spot repair of curbing, resetting of castings, installation of traffic stripes and marking and other incidental roadway items. Fastech is responsible for Construction
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| D&L Paving Contractors, Inc. | $170,176.35 | 07/31/2026 | 07/07/2026 |
Pre-construction meeting was held on 04/28/2026. D & L is scheduled to start work by the mid of July after the summer break starts, with paving to be done soon after.
Project Description:
The scope of the project consists of first phase of Borough-wide Sanitary Sewer Improvements to address the Inflow and Infiltration (I&I) issues. The targeted area is on Hudson Terrace between Kahn Terrace and Sherwood Avenue. There will be two 10 ft areas of point lining and one manhole to manhole lining 237 ft long.
Following is the status of the two 10 ft point linings and one 237 ft lining;
| Contractor | Award Amount | Completion | Last Updated |
|---|---|---|---|
| Montana Construction | $51,100 | 06/01/2026 | 07/07/2026 |
Both parts of Phase 0, which are the emergency repairs, were completed.
Project Description:
The scope of the project consists of second phase of Borough-wide Sanitary Sewer Improvements to address the Inflow and Infiltration (I&I) issues. It consists of 12 distinct repair areas.
| Contractor | Award Amount | Target Completion | Last Updated |
|---|---|---|---|
| National Water Main Cleaning Company | $1,091,150.00 | TBD | 07/07/2026 |
Pre-construction meeting is scheduled for 07/09/2026.
Project Description:
The scope of the project consists of construction of a new roadway on unimproved 5th street from border of the borough to the dead end behind 10 Bayview Avenue. Preliminary design and initial utility investigation is in progress.